Managing Asbestos  

home :: services :: about :: contact

An asbestos hazard in the work environment can be a highly emotive issue, which needs to be carefully managed and communicated to staff, contractors and regulators alike. There are four main phases recommended to protect  occupants and contractors:

  • Awareness
    In the best case scenario, maintenance and building workers and their employers need to have sufficient training and knowledge of where asbestos materials have typically been used and found in the past in  other similar buildings of similar age.  Management must have plans and a historical record of building works conducted in the past to provide valuable information on possible risk locations or types.

    All this information assists in recognising the possibility of an asbestos hazard. When the available historical information is inadequate, the identification of the likely presence or absence of an asbestos hazard is best handled by appropriately trained persons undertaking a hazard audit. The hazard audit involves the identification, evaluation and recommended control of all the identified risks (not just asbestos).

    When the existence of a hazard is recognised, an atmosphere of open consultation between management, workers, parents and employees is the best starting point leading to a technically sound solution which also manages expectations and minimises undue concerns.  This accords with our Facility Ecology approach.
  • Identification

    Considerable care, persistence and awareness is needed to locate all possible occurrences of asbestos. Sampling must be done by trained specialists. Both qualitative and quantitative analysis must be performed to identify the asbestos type and overall potential risk level.

This form of asbestos was typically sprayed (called 'Limpet') onto structural steel beams for its fire insulation properties

  • Evaluation

    Factors such as material condition/damage, friability, accessibility, air plenum, asbestos content, asbestos type, binding material and existing airborne fibre levels must be assessed in order to recommend proper corrective actions. Ensuring legislative requirements are met is another important element.
  • Risk Control

    Options to consider:
  • Deferred action, which is appropriate when there is negligible risk potential, but requires considerable management and custodial care.
  • Enclosure requires an impervious barrier surrounding the asbestos material. Construction of the enclosure itself can generate raised fibre levels and thus the need to carefully monitor such works.
  • Encapsulation or sealing are appropriate if the asbestos (i.e. insulation) is in good condition and can be thoroughly penetrated by the encapsulant. This option should not be employed as a long-term protection nor in areas where access is required.
  • Removal is highly effective in protecting workers and occupants from elevated levels of asbestos fibres. However, this requires an expertly planned, independent and continuous monitoring program during the asbestos removal. This involves a highly detailed tender specification and inspection and discussion phase with the chosen removal contractor.

It should be emphasised that asbestos is not be the only building material hazard.  A concurrent Total Hazard Assessment should always be considered, when asbestos is under review.

CETEC offers risk management of asbestos and other hazardous material in buildings. We have more than 20 years experience in providing independent risk assessment and management. An independent, professionally qualified and trained consultant who bases their control recommendations on appropriate identification and evaluation methods is essential.

To give us feedback on this article or to ask how CETEC can help you then contact us here.



 
Select another article:
Using The Olympics As An Environmental Example
The Cost of Greening Buildings
Agricultural Residues for Biomass Fuels

 

CETEC can help you to minimise your risk whether you are at the pre-project, design, construct, operate, refurbishment or demolition stage.

Call CETEC and FORAY Laboratories:
(03) 9544 9111 or (02) 9351 2455

Head Office:2/27 Normanby Road,
Clayton North, Victoria 3168
NSW:
Chemical Engineering Dept,
University of Sydney, NSW 2006
Email: info@cetec-foray.com.au
Facsimile: (03) 9544 9122
Website: www.cetec-foray.com.au
NATIONALLY